Lockheed Martin will begin a five-month series of flight tests of the MC-130J Combat Shadow after completing first flight on 22 April.
The first MC-130J is scheduled for delivery in September to Cannon AFB, New Mexico, where it will start replacing the Air Force Special Operations Command's MC-130Ps that entered service in 1986.
© Lockheed Martin |
Lockheed designed the MC-130J, which performs low-altitude aerial refuelings for helicopters and tiltrotors, using the KC-130J tanker as the baseline.
© Lockheed MartinThe first MC-130J rolled-out of Lockheed Martin's final assembly plant on 6 April |
AFSOC is planning to deploy the first MC-130J operational unit in fiscal year 2012.
Source: Flight International