- Ares V request for proposals 5 January 2009
- Concept review 21 April 2009
- Phase one contracts awarded Q2 2009
- Functional feasibility review 25 August 2009
- Preliminary requirements review 23 March 2010
- Concept design review December 2010
- Level two system requirement review 2010
- Level three system requirement review 2011
- Authority to proceed 2011
- Level three system definition review 2012
- Phase two DDT&E and production contracts March 2012
- Ares V elements' preliminary design review Q3 2013 to Q1 2014
- Ares V elements' critical design review 2016
- Ares V test flight 2018, first lunar mission December 2019
Source: Flight International