Korean Air will take delivery of 16 aircraft over 2017, including seven Bombardier CS300s.
The SkyTeam carrier disclosed its aircraft delivery schedule with its fourth-quarter results. Besides the CS300s, it is also poised to take three Boeing 747-8 Intercontinentals, five 787-9s and one 777 Freighter.
Delivery of the CSeries aircraft will start in August, with one to be delivered each month to October, before taking two aircraft each in November and December.
KAL will take delivery of its first 787-9 in February, followed by one delivery each in April, July, September and December.
The 747-8Is will be delivered in April, May and July, while the sole 777-200LRF will be delivered in September.
At the end of 2016, KAL had a fleet of 160 aircraft, comprising 129 passenger jets and 31 freighters.
Flight Fleets Analyzer shows that the carrier has 90 aircraft on order, which includes orders for 30 Airbus A321neos and 30 737 Max 8s.
Source: Cirium Dashboard